Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24 days joined them after 4 days. Under the circumstances in how many days the work will be completed?
Given,Â
5 men can complete the work in 8 days
Om Prakash can complete the work in 24 days
Let the total work = 24 unit (LCM of 8 and 24)
Efficiency =Â $$\frac{work}{time\ taken}$$
Efficiency of 5 men =Â $$\frac{24}{8}=3$$
Efficiency of Om Prakash =Â $$\frac{24}{24}=1$$
According to question,Â
5 men worked 4 daysÂ
i.e; work done in four days =Â $$3\times\ 4=12$$
Remaining work = 24 - 12 = 12 units
Now om prakash joinedÂ
time =Â $$\frac{\left(remaining\ work\right)}{efficiency\ of\ working\ persons}$$
=Â $$\frac{12}{3+1}=3$$
So, total Days in completing work = 4 + 3 = 7 days
hence, Option C is correct.Â