A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
Let total work to be done = 100 units
Work done by A in 25 days = $$\frac{75}{100} \times 100 = 75$$ units
A's efficiency = $$\frac{75}{25} = 3$$ units/day
Remaining work = 100 - 75 = 25 units
Let B's efficiency = $$x$$ units/day
Now, A and B complete remaining work in 5 days
=> $$(3 + x) \times 5 = 25$$
=> $$3 + x = \frac{25}{5} = 5$$
=> $$x = 5 - 3 = 2$$
$$\therefore$$ Time taken by B to complete the whole work alone = $$\frac{100}{2} = 50$$ days
=> Ans - (A)
Create a FREE account and get: