Edit MetaData
5 years, 9 months ago
21 women can complete a piece of work in 20 days by working 10 hours a day in how many days 21 men will be complete the work by working 8 hours a day if 3 men work as much as 5 women ?
4 years, 2 months ago
3 men = 5 women
21 men = 35 women
(21*10*20)/(35*8) = 15 days
Day-wise Structured & Planned Preparation Guide
By proceeding you agree to create your account
Free CAT Schedule PDF will be sent to your email address soon !!!