Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs 2860, then what is the share (in Rs) of Raman?
Raman can do a work in 5 days
Jatin can do the same work in 7 days
Sachin can do the same work in 9 days
$$\frac{1}{R+J+S}=\frac{1}{5}+\frac{1}{7}+\frac{1}{9}$$
$$\frac{1}{R+J+S}$$ = $$\frac{63+45+35}{315}$$
$$\frac{1}{R+J+S}$$ = $$\frac{143}{315}$$
$$R+J+S$$ = $$\frac{315}{143}$$
All 3 together can complete the work in $$\frac{315}{143}days$$
if total money earned = 2860, then
Raman's share = $$\frac{1}{5}*\frac{315}{143}*2860 = \frac{63}{143}\times 2860=1260$$
so the answer is option A.