Question 77

A and B together do a job in 6.75 days and A could do the job in 9 days if he worked alone. How many days would B take to do the job if he worked alone?

Solution

Let total work = 27 units

A+B efficiency = 27/6.75 = 4

A's efficiency = 27/9 = 3

B's efficiency = 4-3 = 1

B alone can complete the work in 27/1 = 27 days

So the answer is option A.