A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days. B alone will complete 40% of the same work in:
Let A alone take x days
And B alone take y days
$$\frac{x}{2}+\frac{y}{2}$$= 50
x + y = 100
x = 100 - y
So $$\frac{1}{100-y}+\frac{1}{y}=\frac{1}{24}$$
24y + $$24\left(100-y\right)$$ = $$y\left(100-y\right)$$
24y + 2400 -24y = 100y - $$y^2$$
$$y^2-100y+2400=0$$
$$\left(y-60\right)\left(y-40\right)=0$$y = 40 OR 60
Since A is more efficient , B takes 60 days A takes 40 days
So 40% of the work will take B = $$\frac{40}{100}\times\ 60=24\ days$$Â
Hence, Option B is correct.Â
Create a FREE account and get: