Question 67

A and B can complete a work in 18 days and 10 days, respectively. They worked together for 5 days, after which B was replaced by C and the work was completed in the next 3 days. How long will C alone take to complete the entire work?

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!

Ask AI

Ask our AI anything

AI can make mistakes. Please verify important information.