A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, $$\frac{3}{5}$$ of the work is completed. How many additional men may be employed, so that the work may be completed in time, each man now working 17 hours per day?
$$10\times\ \ \ $$From the formula,
Total work =Â $$\frac{mdh}{w1}$$
here, m = man/woman
d =days
h = hour
w = work
Total work = $$75 \times 187 \times 15$$ = 210375
Work done in 65 days =Â 210375 $$\times \frac{3}{5}$$ = 126255
Remaining work =Â 210375 -Â 126255 = 84150
$$(187 + m) \times 10 \times 17$$ = 84150
(187 + m) = 495
m = 495 -187 = 308
$$\therefore$$ 308Â additional men may be employed, so that the work may be completed in time.
Create a FREE account and get: