A and B can complete a piece of work in 15 days and 20 days respectively. They got a contract to complete the work for ₹77000. The share of A (in ₹) in the contracted money will be:
According to question,
Work done by A in 1 day = $$\frac{1}{15}$$
Work done by B in 1 day = $$\frac{1}{20}$$
Let total time taken to complete the work = $$x$$ days
$$\therefore x(\frac{1}{15}) + x(\frac{1}{20}) = 1$$
$$\Rightarrow \frac{1}{15} + \frac{1}{20} = \frac{1}{x}$$
$$\Rightarrow \frac{4+3}{60} = \frac{1}{x}$$
$$\Rightarrow x = \frac{60}{7} $$ days
So, it will take $$\frac{60}{7}$$ days to complete the work.
$$\therefore$$ Part of work done by A = $$ x(\frac{1}{15}) = \frac{60}{7}\times\frac{1}{15} = \frac{4}{7}$$ of the work.
$$\therefore$$ Share of A = $$77000 \times \frac{4}{7} = ₹44000$$
Create a FREE account and get: