A and B separately can build a wall in 12 and 16 days, respectively. If they work for 1 day alternatively, starting with A, in how many days will the wall be built?
Let the total work = W
Number of days required for A to build the wall = 12 days
$$=$$>Â Work done by A in 1 day = $$\frac{W}{12}$$
Number of days required for B to build the wall = 16 days
$$=$$>Â Work done by B in 1 day = $$\frac{W}{16}$$
Work done by both A and B in 2 days working alternatively for 1 day = $$\frac{W}{12}+\frac{W}{16}=\frac{7W}{48}$$
$$=$$>Â Work done by both A and B in 12 days working alternatively for 1 day = $$\frac{7W}{48}\times\frac{12}{2}=\frac{7W}{8}$$
Remaining work after 12 days = $$W-\frac{7W}{8}=\frac{W}{8}$$
Remaining work after A working on the 13th day = $$\frac{W}{8}-\frac{W}{12}=\frac{W}{24}$$
$$=$$>Â The remaining work $$\frac{W}{24}$$ will be completed by B
Number of days required for B to complete $$\frac{W}{24}$$ =Â $$\frac{\frac{W}{24}}{\frac{W}{16}}=\frac{2}{3}$$ day
$$\therefore\ $$Number of days required to complete the total work = 12 + 1 +Â $$\frac{2}{3}$$ =Â $$13 \frac{2}{3}$$ days
Hence, the correct answer is Option C
Create a FREE account and get: