A, B, and C can do a piece of work in 36 days, 54 days, and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work?
Let's assume the total work is 108 units.
A, B, and C can do a piece of work in 36 days, 54 days, and 108 days, respectively.
Efficiency of A =Â $$\frac{108}{36}$$ = 3 units/day
Efficiency of B = $$\frac{108}{54}$$ = 2 units/day
Efficiency of C = $$\frac{108}{108}$$ = 1 unit/day
They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed.
Let's assume the number of days C worked after A left is 'y'.
$$(3+2+1)\times9 + 2\times(y-3) + 1\times y = 108$$
$$6\times9+2y-6+y=108$$
$$54+3y-6=108$$
48+3y = 108
3y = 108-48 = 60
y = 20
The total number of days C work = (9+y)Â Â Â Â Â [Here 9 is added. because they worked together for 9 days.]
= 9+20
= 29 days
Create a FREE account and get: