To do a certain work, efficiencies of A and B are in the ratio 7:5. Working together, they can complete the work in $$17\frac{1}{2}$$ days. In how many days, will B alone complete 50% of the same work?
Let the total work = 700 units
Efficiencies of A and B are in the ratio 7:5.
Let the efficiency of A and B are 7p and 5p respectively.
Efficiencies of A and B together = 7p + 5p = 12p units/day
Working together, they can complete the work in $$17\frac{1}{2}$$ days.
$$\frac{700}{12p}$$ =Â $$17\frac{1}{2}$$
$$\frac{700}{12p}$$ =Â $$\frac{35}{2}$$
p =Â $$\frac{10}{3}$$
Efficiency of B = 5p =Â $$\frac{50}{3}$$ units/day
Number of days required for B alone complete 50% of the same work = $$\frac{350}{\frac{50}{3}}$$
=Â $$\frac{350\times3}{50}$$
= 21 days
Hence, the correct answer is Option B
Create a FREE account and get: