Question 56

The efficiencies of A, B and C are in the ratio of 5 : 3 : 2. Working together, they can complete a task in 21 hours. In how many hours will B alone complete 40% of that task?

Solution

Total 1 hour work = 2d + 5d + 3d = 10d

Work completed in 21 hours

=> total Work = 21 $$\times$$ 10d = 210d

40% part of work = (40/100) $$\times$$ 210d = 84d

B's 1 hour work = 3d 

B can complete 40% part of that work in = 84d $$\div$$3d = 28

So , the answer would be option b)28.