A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
Let the number of days required for A alone to complete the work = 100a
$$=$$>Â Number of days required for B alone to complete the work = 145a
Let the total work = W
Work done by A in 1 day =Â $$\frac{W}{100a}$$
Work done by B in 1 day = $$\frac{W}{145a}$$
Work done by A and B in 1 day = $$\frac{W}{100a}+\frac{W}{145a}=\frac{245W}{14500a}=\frac{49W}{2900a}$$
Work done by A and B in 58 days$$=58\times\frac{49W}{2900a}=\frac{49W}{50a}$$
Remaining work $$=W-\frac{49W}{50a}$$
Remaining work is completed by B in 29 days
$$=$$>Â $$W-\frac{49W}{50a}=\frac{29W}{145a}$$
$$=$$> Â $$W=\frac{29W}{145a}+\frac{49W}{50a}$$
$$=$$> Â $$W=\frac{1450W+7105W}{145\times50\times a}$$
$$=$$> Â $$W=\frac{8555W}{145\times50\times a}$$
$$=$$> Â $$W=\frac{59W}{50a}$$
$$=$$> Â $$50a=59$$
$$=$$> Â $$100a=118$$
$$\therefore\ $$Number of days required for A alone to complete the work = 100a = 118 days
Hence, the correct answer is Option B
Create a FREE account and get: