A does 60% of a work in 15 days. He then calls B, and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
Let total work to be done = 100 units
Work done by A in 15 days = $$\frac{60}{100} \times 100 = 60$$ units
A's efficiency = $$\frac{60}{15} = 4$$ units/day
Remaining work = 100 - 60 = 40 units
Let B's efficiency = $$x$$ units/day
Now, A and B complete remaining work in 5 days
=> $$(4 + x) \times 5 = 40$$
=> $$4 + x = \frac{40}{5} = 8$$
=> $$x = 8 - 4 = 4$$
$$\therefore$$ Time taken by B to complete the whole work alone = $$\frac{100}{4} = 25$$ days
=> Ans - (A)
Create a FREE account and get: