A can do a work alone in 10 days. B can do the same work alone in 15 days. They start together but B leaves the job 2 days after start and A completes the remaining work alone. What is the total number of days in which the work is completed?
Let's assume the total work is 30 units.
A can do a work alone in 10 days.
Efficiency of A =Â $$\frac{30}{10}$$ = 3 units/day
B can do the same work alone in 15 days.
Efficiency of B = $$\frac{30}{15}$$ = 2 units/day
They start together but B leaves the job 2 days after start and A completes the remaining work alone.
Let's assume the number of days A work alone is 'y'.
$$(3+2)\times2 + 3y = 30$$
$$5\times2 + 3y = 30$$
10Â + 3y = 30
3y = 30-10 = 20
$$y=\frac{20}{3}$$
The total number of days in which the work is completed =Â $$2+y$$
=Â $$2+\frac{20}{3}$$
= $$\frac{6}{3}+\frac{20}{3}$$
= $$\frac{26}{3}$$ days
Create a FREE account and get: