Question 159

56 workers are finish a piece of work in 14 days. If the work is to be completed in 8 days, how many extra workers are required?

Total Man-days = 56*14
Number of days = 8

Number of workers = 56*14/8 = 7*14
Total number of workers = 98
Additional workers = 98-56 = 42