Question 15

A is 40% more efficient than B. If B alone can complete a work in 42 days, then A alone can complete the same work in how many days?

Solution

Let total work to be done = 42 units

B can complete the work in 42 days, => B's efficiency = $$\frac{42}{42}=1$$ unit/day

A is 40% more efficient than B, => A's efficiency = $$1+(\frac{40}{100}\times1)=1.4$$ units/day

$$\therefore$$ Time taken by A = $$\frac{42}{1.4}=30$$ days

=> Ans - (C)