Question 124

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/ 3 of the work. How many men can be discharged now so that the work may finish in time ?

Solution

Let's assume the number of men dischanger after 64 is y.

$$\frac{M1 \times D1 }{W1}$$ = $$\frac{M2 \times D2}{W2}$$

$$\frac{64\times120}{\frac{2}{3}} = \frac{(124-64)\times(120-y)}{\frac{1}{3}}$$

$$\frac{64\times120}{2} = \frac{60\times(120-y)}{1}$$

$$\frac{64\times60}{1} = \frac{60\times(120-y)}{1}$$

64 = 120-y

y = 120-64 = 56


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App