Question 131

The length, width and height of a wall are given as 800 cm, 500 cm and 50 cm respectively. What will be the total cost (Rs.) of brickwork, if the rate of brickwork is Rs. 320 per cubic metre?

Video Solution
Question 132

The plinth area rate and plinth area of a building is Rs 5500 per sq.m and 150 sq.m respectively. What is the total cost (Rs.) of building considering cost of electrification as 7%, cost of sanitary fittings as 16%, cost of roads and lawns as 6.5% and cost of contingencies as 4.5%.

Video Solution
Question 133

Which of the following item is NOT a lump sum item?

Video Solution
Question 134

What is the total cost (Rs.) according to approximate estimate of hostel building with capacity of 75 beds? The altogether cost per bed is given as Rs. 20,000.

Video Solution
Question 135

What is the volume of earthwork (cubic metre) in embankment of 10 m long and
7m wide with the side slope of 2:1?

Video Solution
Question 136

Which of the following method is used to prepare the approximate estimate?

Video Solution
Question 137

In which of the following condition two contour lines intersect each other?

Video Solution
Question 138

Which of the following scale of the map is not affected due to shrinking of map?

Video Solution
Question 139

A surveyor measures a distance between two points on a map of representative fraction of 1:100 is 60 m. But later he found that he used wrong  representative fraction of 1:50. What is the correct distance between the two points?

Video Solution
Question 140

Which one of the following is the CORRECT statement for a station that is affected by local attraction?

Video Solution