The following pie-chart shows the sources of funds (InRs. crores) to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answer the following Three questions
If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores ?
Amount required to support the project = 4910 crore
Maximum compensation = 10%
=> 10% of 4910 cr = $$\frac{10}{100} * 4910 cr = 491 cr
Amount permitted = 4910 cr + 491 cr = 5401 cr