B is 1.5 times as efficient as A. If A can complete $${6 \over 7}$$th of a given task in 12 days, what fraction of the same task would remain incomplete if B works on it independently for 6 days only?
Let efficiency of A = $$2x$$ units/day
=> Efficiency of B = $$1.5 \times 2x = 3x$$ units/day
Let Work to be done = 7 units
=> Work done by A in 12 days = $$12 \times 2x = \frac{6}{7} \times 7$$
=> $$24x = 6$$
=> $$x = \frac{6}{24} = \frac{1}{4}$$
Thus, B's 1 day work = $$3 \times \frac{1}{4} = \frac{3}{4}$$ units
Work done by B in 6 days = $$\frac{3}{4} \times 6 = \frac{9}{2}$$ units
=> Work left = $$7 - \frac{9}{2} = \frac{5}{2}$$
$$\therefore$$ Fraction of work left = $$\frac{\frac{5}{2}}{7}$$
= $$\frac{5}{14}$$
Create a FREE account and get: