8 men can finish a piece of work in 21 days. 14 men started working and after 3 days were replaced by 9 women. These 9 women finished the remaining work in 24 days. In how many days 9 women can finish the whole work ?
Let efficiency of 1 man = $$x$$ units/day
Efficiency of 1 woman = $$y$$ units/day
Since, 8 men finish the work in 21 days
Let total work = $$x \times 8 \times 21 = 168x$$ units
Initially, 14 men worked for 3 days
=> worked completed = $$x \times 14 \times 3 = 42x$$ units
Work left = $$168x - 42x = 126x$$ units ---------------------(i)
Now, 9 women complete this work in 24 days
=> work done by women = $$y \times 9 \times 24 = 216y$$ units --------(iI)
From eqn (i) & (ii), we get : $$126x = 216y$$
=> $$\frac{x}{y} = \frac{216}{126} = \frac{12}{7}$$
$$\therefore$$ Number of days taken by 9 women to finish the work
= $$\frac{168x}{9y} = \frac{168}{9} \times \frac{12}{7}$$
= $$24 \times \frac{4}{3} = 32$$ days
Create a FREE account and get: