SSC JE Civil Engineering 27th Jan 2018 Shift-1

Instructions

For the following questions answer them individually

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 111


What percentage of the cost of the estimate is provided for the tools and plants?

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 112


What is the thickness (cm) of a two brick wall made up of standard modular brick?

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 113


The expected out turn (cubic metre) of reinforced brickwork per mason per day is _____.

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 114


A canal bank has a length of 100 m and its height at two extreme ends is 2 m and 3 m respectively. The side slope of the bank is 2 : 1. The rate of pitching is Rs. 500 per square metres. Calculate the cost (Rs.) of pitching of the area of the side slope.

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 115


Calculate the volume (cubic metre) of the dry mortar required for 1 cubic metre brick work.

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 116


Which of the following is a factor for obsolescence of the property?

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 117


Calculate the years purchase for a property of useful life of 30 years and rate of interest of 5% per annum. The rate of interest for sinking fund is 3%.

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 118


The expression for the total volume of earthwork for an embankment using Simpson's one third rule, if $$A_1, A_2, A_3, A_4, ........, A_{n - 1}$$ and $$A_n$$ are the areas at n sections at an interval of h is ..............

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 119


Which of the following quantity is measured using a Planimeter?

SSC JE Civil Engineering 27th Jan 2018 Shift-1 - Question 120


The inside wall of a septic tank is finished with 12 mm cement plaster with 1 : 4 cement mortar. Calculate the quantity of the cement (cubic metre) required, if the size of the septic tank is 6 m $$\times$$ 4 m $$\times$$ 2 m.