SSC JE Civil Engineering 24th Jan 2018 Shift-1

Instructions

For the following questions answer them individually

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 171


Which of the below is not a plaster finish?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 172


If the depth of moist sand in a cylinder is 15 cm and the depth of the sand when fully inundated with water is 12 cm, then what is the bulking of the moist sand?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 173


If P, Y and Z are weights of cement, fine aggregates and coarse aggregates respectively and W/C is the water cement ratio, the minimum quantity of water to be added to first batch is obtained by the equation

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 174


How do we reduce the shrinkage in concrete?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 175


Which of the following are the specifications of a cement bag for storage?
A. weight 50 kg
B. height 18 cm
C. plan area 300 0 sq.cm
D. volume 35 liters

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 176


What should be done to ensure constant moisture content in aggregates?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 177


For batching 1:3:6 concrete mix by volume, which of the following are the ingredients required per bag of 50kg cement?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 178


Which of the following statements is/are true?

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 179


In a R.C.C structure, the tension zone lies in the:

Video Solution

SSC JE Civil Engineering 24th Jan 2018 Shift-1 - Question 180


In a Pre Stressed Concrete, the tensioning system may be classified into:

Video Solution