Consider the following statement associated with the critcal path :
1.critical path is the most important sequence of activities which has no float and which determine the project completion period
2.critical path is the largest path with shortest duration with in which the project can be completed
3.The difference between early start time and late finish time must be equal to the activity duration
4.can not pass through dummy activity
which is among the above are correct statements