6 men finish one-fourth work in 2 days. The number of additional men required for finishing the same work in 2 days is
Time taken by 6 men to finish the whole work = 8 days
Let the number of men required be x.
Less days, more men (Inverse Proportion)
Days Men
8 6
2 x
⇒ x =(8 * 6)/2 = 24 men
The additional men required = 24-6 men= 18 men