A can do a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work together but A and B left 8 days and 12 days before the completion of the work respectively. How many days in all did C put in till the entire work was finished?
Let total time taken to complete the work = 'x' days
C work for 'x' days.
A left 8 days before the completion of the work. So, A works for 'x - 8' days
B left 12 days before the completion of the work. So, B works for 'x - 12' days
Now,
$$\frac{x - 8}{36} + \frac{x - 12}{54} + \frac{x}{72} = 1$$
$$\frac{6(x - 8) + 4(x - 12) + 3x}{216} = 1$$
6x - 48 + 4x - 48 + 3x = 216
x = 24
Hence, C works for total 24 days.