Type 1 workers can do three times the work of Type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 8 Type 2 workers to complete the same task?
Type 1 Worker-
12 Type 1 workers can complete the work in 10 days.
So, 1 Type 1 workers can complete the work in 12x10 days i.e. 120 days.
Type 1 workers 1 day's work= 1/120.
4 Type 1 workers 1 day's work= 4/120= 1/30.
Since, the Type 1 is 3 times efficient than Type 2. So,
Type 2 Worker-
1 Type 2 workers can complete the work in 12x10x3 days i.e. 360 days.
Type 2 workers 1 day's work= 1/360.
8 Type 2 workers 1 day's work= 8/360= 1/45.
So, 1 day's work of Type 1 and Type 2 workers= 1/30+1/45= 1/18.
So, total time taken to complete the work= 18 days.
Therefore, Option D is correct.