Sign in
Please select an account to continue using cracku.in
↓ →
40 men can complete the work in 48 days. 64 men started and did the same work for x days. After x days, 32 men increased, so the remaining work is completed in $$16\dfrac{2}{3}$$ days, then what is the value of x?
Let efficiency of work done by a man be 1 unit/day.
So, total units of work = $$40\times\ 48\times\ 1=1920$$ units
Now, if 64 men worked for x days, so amount of work done = $$64\left(x\right)\left(1\right)=64x$$ units
Now, after x days, total number of men = $$64+32=96$$
So, work done by these 96 men in $$16\ \dfrac{2}{3}$$ days = $$96\times\ 1\times\ 16\ \dfrac{2}{3}$$ units = $$96\times\ 1\times\ \dfrac{50}{3}=1600$$
So, we can say,
$$1920=64x+1600$$
or, $$1920-1600=64x$$
or, $$64x=320$$
or, $$x=\dfrac{320}{64}=5$$
So, value of $$x$$ is 5.
Click on the Email ☝️ to Watch the Video Solution
Crack IPMAT 2026 with Cracku
Educational materials for IPMAT and IIMB UG preparation
Ask our AI anything
AI can make mistakes. Please verify important information.
AI can make mistakes. Please verify important information.