Which of the following statements regarding project management is true?
Crash cost depends upon the variance of the activity to be crashed
Both PERT and CPM require that net work tasks have un changing durations
Shortening the project by assigning more resources to one or more of the critical tasks is called project crashing
Crashing need not consider the importance of crashing an activity on other parts in the network