Question 15

Which of the following doesn't fit into the series?
5-1-96, 27-1-96, 18-2-96, 12-3-96, 2-4-96.

Solution

5-1-96, 27-1-96, 18-2-96, 12-3-96, 2-4-96.

These are dates, and each of them should have 22 days in between, but for dates between 18-2-96 and 12-3-96 there are 23 days,

so 12-3-96 doesnt fit the series.

Option C is correct.