Question 108

24 Men can complete a piece of work in 15 days. In how many days will 18 men complete that work ?

Solution

24 men can complete the work in 15 days.
So, 1 man can complete the work in 15*24 = 360 days.

Hence, 18 men can complete the work in $$\frac{360}{18}=20$$ days