SSC JE Civil Engineering 29th Jan 2018 Shift-1

Instructions

For the following questions answer them individually

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 111


What is the unit of measurement for steel reinforcement?

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 112


What is the weight (in kg) per meter length for 12 mm diameter steel bar?

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 113


What percentage of the total cost is added in the cost of construction for contingencies?

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 114


What percentage of total cost is added to the schedule of rates of the public work department for over-head cost?

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 115


For estimation of painting area of corrugated sheets, percentage increase in area above the plain area is ____.

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 116


Central line method for estimation is suitable for_______

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 117


Deduction at the L-junction of wall for total length of the central line is ______________.

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 118


Calculate the quantity of the cement required in cubic meter for 10 square meters of cement plaster 12 mm thick using cement mortar of 1:6.

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 119


Calculate the quantity of the earthworks in cubic meter for a canal embankment of 100 m long having heights of 3 m and 5 m at the two extreme edges. Top widths of the embankment are 2 m and 4 m at the two extreme edges and side slope is 2: 1. Use trapezoidal method.

Video Solution

SSC JE Civil Engineering 29th Jan 2018 Shift-1 - Question 120


Calculate the primary estimate including contractor’s profit in rupees for the building having a plinth area of 1,500 square meters and a rate of Rs. 2,000 per square meter.