SSC JE Civil Engineering 25th Jan 2018 Shift-2

Instructions

For the following questions answer them individually

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 111


Which one of the following shows total quantities of all the items of materials
required for the completion of the construction?

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 112


Grouting of the cracks is measured in _____.

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 113


Which of the following is NOT measured in square metre?

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 114


The expected out turn (square metre) of sawing of the soft wood per mason per
day is _____.

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 115


Which of the following is the multiplying factor for the estimation of lead for sandy
tracks?

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 116


What is the thickness of one and half brick wall made up of standard modular
brick?

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 117


Calculate the approximate estimate of a four storey building, if the total plinth
area is 300 square metres per floor and height of floor is 3 m. The cubical
content rate is Rs. 2,000 per cubic metre and the profit of the contractor is 10% of the total cost.

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 118


Calculate the quantity(cube m) of brick work for a room using the central line
method, if the interior dimension of the room is 5 m x 4 m and height of the room is 3.5 m. The
width of the wall is 300 mm and dimension of the door is 2 m x 1.2 m.

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 119


In the straight line method, the expression for depreciation of a machine having
purchasing cost C, scrap value S and useful life of the machinery n, is _____.

Video Solution

SSC JE Civil Engineering 25th Jan 2018 Shift-2 - Question 120


Calculate the number of bags of cement required for the 12 mm thick plastering
of a wall of 5 m long, 3.5 m high and 300 mm thick, if 1 : 3 cement mortar
is used.

Video Solution