For the following questions answer them individually
Calculate the quantity of the sand required (in cubic meter) in 20 cubic meters of reinforced cement concrete (1 : 2 : 4)
Calculate the quantity of the earth works in cubic meter for a canal embankment of 100 m long having cross section areas at the two sections are 20 square meters and 80 square meters. Use trapezoidal method.
For estimation of painted area of corrugated asbestos cement sheets, percentage increase in area above the painted area is _____
An electric generator is installed in the building at a cost of Rs. 50,000. Calculate the annual sinking fund (Rs.) required to be deposited to accumulate the whole amount of 5% compound interest. Assume the life of the electric generator as 10 years.
- Calculate the weight (kg) per meter length of 25 mm diameter steel bar place at a spacing of 250 mm center by center for 1 meter.