Time and Work Questions for LIC AAO PDF Set-2
Download Important Time & Work questions for LIC AAO exam. Top 20 Time & Work questions set-2 with answers based on previous year asked questions.
Download Time and Work Questions for LIC AAO PDF
Download LIC AAO Time & Work Set-1 Questions PDF
Take a free mock test for LIC AAO
Download LIC AAO Previous Papers PDF
Question 1: A-B means A is the father of B. A+B means A is the daughter of B. $A\div B$ Means A is the son of B. $A\times B$ means A is the wife of B . Then, what is the relation of P with T in the expression P+S-T?
a) Son
b) Daughter
c) Sister
d) Wife
Question 2: 12 year old Mahesh is three times as old as his brother Ramesh. How old will Mahesh be when he is twice as old as Ramesh ?
a) 14 years
b) 20 years
c) 18 years
d) 16 years
Question 3: 9 children can complete a piece of work in 360 days, 18 men can complete the same piece of work in 72 days and 12 women can complete it in 162 days. In how many days can 4 men, 12 women and 10 children together complete the piece of work ?
a) 68 days
b) 81 days
c) 96 days
d) 124 days
Download LIC AAO Previous Papers PDF
100 Free Computer Awareness Tests for LIC
Question 4: 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work ?
a) 3
b) 5
c) 7
d) Cannot be determined
Question 5: 8 men can finish a piece of work in 40 days. If 2 more men join with them, then the work will be completed in
a) 30 days
b) 32 days
c) 36 days
d) 25 days
Question 6: A man, a woman and a boy together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman take to complete the work ?
a) 9 days
b) 21 days
c) 24 days
d) 27 days
Question 7: A, B and C can do a piece of work in 20, 25 and 40 days. They started the work together but B left 4 days before completion. In how many days the work is completed?
a) 13$\large\frac{4}{23}$ days
b) 10$\large\frac{2}{23}$ days
c) 12$\large\frac{3}{17}$ days
d) 14$\large\frac{5}{17}$ days
e) None of these
100 Free GK Tests for Insurance Exams
Question 8: 5 men and 13 women can do a piece of work in 5 days while 2 men and 7 women can do the same work in 11 days. Then in how many days can 4 men and 6 women can complete the work?
a) 8$\large\frac{1}{2}$ days
b) 6$\large\frac{1}{3}$ days
c) 7$\large\frac{1}{2}$ days
d) 9 days
e) None of these
Question 9: A can do a piece of work in 24 days. B can do the same work in 36 days. With the help of C, the work has finished in 9 days. If total wage for doing the work is Rs.6400, then the amount received by C is
a) Rs. 2400
b) Rs.1800
c) Rs.1600
d) Rs.2000
e) None of these
Question 10: A and B can do a piece of work in 15 days and 20 days respectively. They work in alternate days starting with A. In how many days, total work will be completed?
a) $16\frac{1}{3}$ days
b) $17\frac{1}{4}$ days
c) 17 days
d) 15 days
e) None of these
LIC AAO REASONING QUESTIONS PDF
Answers & Solutions:
1) Answer (C)
P + S means P is the daughter of S and S – T means S is the father of T.Thus S is the father of both P and T.∴P is the sister of T.
2) Answer (D)
age of Mahesh=12
Given, Mahesh is 3 times as old as Ramesh.
So age of Ramesh is=4
From options, we can see that when we put Mahesh’s age to be 16, we get the age Ramesh to be 8.
∴ when Mahesh is 16 his age is twice that of Ramesh.
3) Answer (B)
Let the speed of child, man and woman to complete work W be x,y and z respectively.
Therefore, as per given conditions
x = W/3240
y= W/1296
and z = W/1944
Now, the combined speed of 4 men, 12 women and 10 children = 4y+12z+10x = W/81
Now, number of days = W/(W/81) = 81 days
The correct option is option B
4) Answer (C)
Let the speed of Women be x and that of children be y. Let piece of work be W.
10x=W/7, x=W/70
10y =W/14 y= W/140
Now, 5x + 10y = W/14 + W/14 = W/7
Number of day srequired to complete the work = W/(W/7) = 7 days.
Therefore, the correct option is option C.
5) Answer (B)
Let the work be W and speed of each man be x.
W/(8x) = 40
x = W/320
If two more men join, total speed will become = W/32
Now, the work can be done= W/(W/32) = 32 days
Therefore work will be done in 32 days.
Download General Science Material PDF
6) Answer (A)
Let the man’s, woman’s and boy’s speed be x, y and z.
Let the piece of work be W.
Now, x+y+z = W/3
Also, x = W/6
and z=W/18
Therefore, y = W/3 – W/6 – W/18
y = W/9
Number of days required by woman alone to complete the work = W/y = W/(W/9)
Hence, number of days = 9
Therefore, the correct option is option A.
7) Answer (B)
A can do the work in 20 days
B can do the work in 25 days
C can do the work in 40 days
Total work = LCM of 20,25,40 $=$ 200 units
Efficiency of A $=$ $\Large\frac{200}{20}$ $=$ 10 units/day
Efficiency of B $=$ $\Large\frac{200}{25}$ $=$ 8 units/day
Efficiency of C $=$ $\Large\frac{200}{40}$ $=$ 5 units/day
Let the number of days required to complete the work be ‘X’ days
Total work done by A in X days $=$ 10 $\times$ X $=$ 10X units
Total work done by C in X days $=$ 5 \times X $=$ 5X days
B left 4 days before completion
Total work done by B in (X – 4) days $=$ 8(X – 4) $=$ (8X – 32) units
$\therefore$ 10X + 5X + 8X – 32 $=$ 200
23X – 32 $=$ 200
$\therefore$ X $=$ $\Large\frac{232}{23}$ $=$ 10$\Large\frac{2}{23}$ days
8) Answer (C)
No. of men$_{1}$ $\times$ No. of days$_{1}$ $=$ No. of men$_{2}$ $\times$ No. of days$_{2}$
$\Rightarrow$ (5M+13W)5 $=$ (2M+7W)11
$\Rightarrow$ 25M + 65W $=$ 22M + 77W
$\Rightarrow$ 3M $=$ 12W
$\therefore$ 1M $=$ 4W
Let the number of days required for 4 men and 6 women to complete the work be ‘x’ days
(5M + 13W) $\times$ 5 $=$ (4M + 6W) $\times$ x
Substituting M $=$ 4W in above equation
$\Rightarrow$ (20M + 13W) $\times$ 5 $=$ (16M + 6W) $\times$ x
$\Rightarrow$ 33W $\times$ 5 $=$ 22W $\times$ x
$\Rightarrow$ x $=$ $\Large\frac{33 \times 5}{22}$ $=$ $\Large\frac{15}{2}$ $=$ 7$\Large\frac{1}{2}$ days
9) Answer (A)
A can do a piece of work in $24$ days
B can do the same work in $36$ days
A+B+C can do it together in $9$ days
Total work $=$ LCM of $24$,$36$,$9$ $=$ $72$ units
Efficiency of A $=$ $\Large\frac{72}{24}$ $=$ $3$ units/day
Efficiency of B $=$ $\Large\frac{72}{36}$ $=$ $2$ units/day
Efficiency of A $+$ B $+$ C $=$ $\Large\frac{72}{9}$ $=$ $8$ units/day
\Rightarrow Efficiency of C $=$ $8$ $-$ $5$ $=$ $3$ units/day
Total efficiency of A $+$ B $+$ C $=$ $8$ units
Total wages $=$ Rs.$6400$
$8$ units $\rightarrow$ Rs.$6400$
$1$ unit $ \rightarrow$ Rs.$800$
then C’s wage $=$ $3\times800$ $=$ Rs.$2400$
10) Answer (C)
A can do a piece of work in $15$ days
B can do the same in $20$ days
Total work $=$ LCM of $15$ and $20$ days $=$ $60$ units
Efficiency of A $=$ $\Large\frac{60}{15}$ $=$ $4$ units/day
Efficiency of B $=$ $\Large\frac{60}{20}$ $=$ $3$ units/day
They work in alternate days starting with A
So, A and B can do $7$ units in $2$ days
So, $56$ units can be completed in $16$ days
Remaining $4$ units can be completed by A in $1$ day
$\therefore$ total work can be completed in $17$ days