3 men and 5 boys can complete a task in 15 days; whereas 6 men and 7 boys can complete the same task in 9 days. Find the relationship between the task done by the boys and the task done by the men.
The work of 4 boys is equivalent to the work of 3 men
The work of 6 boys is equivalent to the work of 2 men
The work of 3 boys is equivalent to the work of 4 men
The work of 7 boys is equivalent to the work of 3 men
Create a FREE account and get:
Quant Based LR
Maxima-Minima
DI Miscellaneous
Charts
Special Charts
Arrangement
Data change over a period
DI with connected data sets
Selection With Condition
Puzzles
Table with Missing values
Quant Based DI
Games and Tournamnents
Miscellaneous LR
Data Interpretation
Truth Lie Concept
Routes And Networks
Coins and Weights
Data Interpretation Basics
Venn Diagrams
Scheduling
2D & 3D LR
Login to your Cracku account.
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!