A and B can complete a piece of task together in 12 days while A alone can doit in 15
days. They start working together but A leaves 10 days before the completion ofthe task. For how many days did A and B work together?
Let the number of days taken by A to complete work as a.
Let the number of days taken by B to complete work as b.
So , according to question ,
$$\frac{1}{a} + \frac{1}{b} = \frac{1}{12}$$
=>Â $$\frac{1}{15} + \frac{1}{b} = \frac{1}{12}$$ =>$$ \frac{1}{b} = \frac{1}{60}$$
So , B takes 60 days to complete the task.
A/c the question , they worked together for some days and B worked alone for 10 days. Let x be the number of days they worked together.
$$(\frac{1}{15} + \frac{1}{60})x + \frac{1}{60} \times 10Â = 1$$
$$\frac{1}{x} = \frac{1}{10}$$
So , the answer would be option b)10 days.
Create a FREE account and get: