Question 1: A certain number of men can do a piece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is

a) 6
b) 12
c) 18
d) 24

Question 2: If the speed of a boat in still water is 20 km/hr and the speed of the current is 5 km/hr, then the time taken by the boat to travel 100 km with the current is

a) 2 hrs
b) 3 hrs
c) 4 hrs
d) 7 hrs

Question 3: If 100 cats kill 100 mice in 100 days, then 4 cats would kill 4 mice in how many days?

a) 4 days
b) 3 days
c) 40 days
d) 100 days

Question 4: Ravi has a roadmap with a scale of 1.5 cm for 18 km. He drives on that road for 72 km. What would be his distance covered in that map.

a) 4 cm
b) 6 cm
c) 8 cm
d) 7 cm

Question 5: A and B together can do a piece of work in 12 days while A alone can do the same work in 30 days. B alone can do it in

a) 18 days
b) 20 days
c) 15 days
d) 22 days

Take a Free Mock test for SBI PO

SBI PO Solved Previous Papers

Question 6: A and B can together do a piece of work in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is

a) 18 days
b) 24 days
c) 9 days
d) 12 days

Question 7: A gun is fired at a distance of 6.64 km away from Ram. He hears the sound 20 seconds later. Then the speed of sound is

a) 664 m/s
b) 664 km/s
c) 332 m/s
d) 332 km/s

Question 8: A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is

a) 4 days
b) 6 days
c) 8 days
d) 12 days

Question 9: A and B start running at the same time and from the same point around a circle. If A can complete one round in 40 seconds and B in 50 seconds, how many seconds will they take to reach the starting point simultaneously?

a) 10
b) 200
c) 90
d) 2000

Question 10: A spaceship travels at 1,260 km/h. How many metres does it travel in 1/10 th of a second?

a) 126
b) 35
c) 36
d) 125

Banking 1 Year Plan – 350 Mocks for just Rs. 499

Daily Free GK – Current Affairs Tests

Answers & Solutions for SBI PO Time and Work Questions PDF:

1) Answer (B)
Let the number of men initially working be x who could finished the work in 60 days
Now, (x+6) men can finish the work in 60 – 20 = 40 days
=> X x 60 = (x + 6) × 40
=> 3x = 2x + 12
=> 3x − 2x = x = 12
∴ The number of men working = 12
=> Ans – (B)

2) Answer (C)
Speed of boat = 20 km/hr and speed of current = 5 km/hr
Distance to travel = 100 km
Speed downstream (with the current) = 20 + 5 = 25 km/hr
=> Time taken = distance / speed
= 100 / 25 = 4 hours
=> Ans – (C)

3) Answer (D)
Let M be the total number of mice killed, c be the number of cats, i be the number of days and e be the average number of mice killed by one cat in one day.
The number of mice killed is proportional to both the number of cats and the number of days.
=> m = ice
Substituting M=100, i = 100 and c = 100 into this equation, we find :
=> 100 = 100 × 100 × e
=> Ans – (D)
=> e = 1 / 100
Thus, substituting M = 4, c = 4, and e = 1 / 100 to get:
=> 4 = i × 4 × 1 /100
=> i = 100 days
=> Ans – (D)

4) Answer (B)
According to the road map 18 km ≡ 1.5 cm
=> 72 km ≡ 15 / 8 × 72
= 1.5 × 4 = 6 cm
=> Ans – (B).

5) Answer (B)
Let total work to be done = 60 units
A can complete the work in 30 days
=> A’s efficiency = 60 / 30 = 2 units/day
Similarly, (A+B)’s 1 day’s work = 60 / 12 = 5 units/day
=> B’s efficiency = 5 − 2 = 3 units/day
∴ B alone can do the work in = 60 / 3 = 20 days
=> Ans – (B)

Banking Online Daily Tests

6) Answer (A)
Let total work to be done = 18 units
A and B can together do the work in 6 days
=> (A+B)’s 1 day’s work = 18 / 6 = 3 units/day
Similarly, A’s efficiency = 18 / 9 = 2 units/day
=> B’s efficiency = 3 − 2 = 1 unit/day
∴ Time taken by B alone = 18 / 1 18 days
=> Ans – (A)

7) Answer (C)
Distance of gun from Ram = 6.64 km = 6640 m
Time = 20 seconds
=> Speed of sound = distance/time
= 6640 / 20 = 32 m/s
=> Ans – (C)

8) Answer (D)
A does thrice the work of B in a given time.
Let B’s efficiency = x units/day
=> A’s efficiency = 3x units/day
Thus, (A+B)’s 1 day’s work = x+3x=4xx+3x=4x units/day
=> Total work done by them in 9 days = 4x \times 9=36x4x×9=36x units
∴ Time taken by A alone to finish the work = 36x / 3x = 12days
=> Ans – (D)

9) Answer (B)
Time taken by A to complete 1 round = 40 seconds and by B = 50 seconds
=> Time taken by them to reach the starting point simultaneously = L.C.M.(40,50)
= 200 seconds
=> Ans – (B)

10) Answer (B)
Speed = 1260 kmph = 1260*(5/18) m/s = 350 m/s
In 1 second it travels 350 meters
In 1/10th second it travels 350/10 = 35 meters.
So the answer is option B.